We were awarded new project to supply 159.47 tons of handrails
We were awarded the Phase III Haikou municipal solid waste incineration power plant project by State Power Investment Corporation Limited(SPIC)
This project will construct three incinerators, each of them can dispose 600 tons waste per day, therefore they can dispose 1800 tons waste per day in all. Besides, this power plant will be configured two sets of 20MW generators with 40MW installed capacity totally. The total investment of this project is about 770 million yuan.
Our company won the bidding to supply about 159.47 tons of handrails which will use φ51mm seamless tubes,and the treatment of the handrails will be hot dip galvanized.
Feel free to contact with us for more details about ball connected handrails, gratings, stair treads, etc.:
contact person:Amber Wu
Phone/whatsapp: +86 18562239900
Email: amber@ythlss.com